FG to shut Third Mainland Bridge, Lagos-Ibadan Expressway after Christmas

starconnect
starconnect
Third Mainland Bridge and Lagos –Ibadan Expressway to be closed to traffic
The Third Mainland Bridge, Lagos

 

Admin l Tuesday, 22 December 2020

LAGOS, Nigeria – Federal Controller of Works( Lagos), Engr. Olukayode Popoola has announced a 72-hour total closure of the Third Mainland Bridge to enable contractors  cast concrete on the expansion joints.

Mr. Popoola  told NAN  that the Third Mainland Bridge will be shut from midnight  Saturday, December 26th  to midnight on Tuesday, December 29th, 2020.

Mr. Popoola who also announced a 48 hours closure on the Lagos/Ibadan Expressway  from Dec 28 to Dec 29 to complete some work on a fly over bridge  along the Lagos /Ibadan Expressway.He added that construction works had reached the stage for casting concrete on additional three expansion joints.

“There is going to be total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane. The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.

“By the time the Christmas is winding down which is 12:00 midnight, we are going to close it so that we will be able to cast the concrete on Saturday the 26th and 27th we cast again.

“And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure. This is to prevent vibration of the bridge. If we allow vehicles to be moving on one lane, there is going to be vibrations and the concrete will not set properly,”he said.

The controller said all the alternative routes were in good condition and traffic regulatory agencies had been deployed to effectively divert and manage traffic to avert gridlock.

Mr Popoola also announced a 48-hour partial closure of the Lagos-Ibadan Expressway from Dec 28 to Dec 29 to complete some work on a fly over bridge on the project.

“The contractor, Messers Julius Berger wants to install cross beams at Kilometre 16, that is, around MFM,” he said. He explained that the piers were already standing on both sides of the road and the contractor was to lay the cross beam on top across the road.

“That area will be cordoned off, there will be closure within that section from 12:00pm on 28th of December and it will be opened to traffic by 5:00am the following day.

” 200 meters to get to that particular location we have diversion and another diversion 200 meters away from that place.

“One lane will be opened to traffic, it is only one lane we are closing to traffic at a time. The first lane that we are going to close is outward Lagos, that is the Ibadan bound carriageway, we will close it on the 28th.

” And then the second day which is 29th, we are moving to the other lane which in inward Lagos. The same 12:00pm to 5:00am,” Popoola said.

 

Share this Article
Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Be the first to get the news as soon as it breaks Yes!! I'm in Not Yet
Verified by MonsterInsights